The schedule of events for the next month are as follows:
October 16: Internal Dome surfaces are completed or paved, parking lots are paved
October 26: Dome arrives on site.
October 31: Turf Fields are installed.
November 5: Dome is inflated.
November 6: Lights and insulation installation begins
November 11: Track/Basketball/Volleyball Courts installation begins
November 21: Dome Opens for Play. Please note opening date change.