2009
Click images to view enlargement.
These are all shots from the entrance of the driveway onto the property. Construction of this beautiful facility done by Orlando Annulli and Sons, Inc.
March 09 - Raw land prior to any clearing.
|
April 09 - Starting to clear the trees.
|
May 09 - Trees are cleared and starting to move dirt. Blasting on back wall will start soon.
|
June 09 – Blasting the back hill, and starting to shape the elevations.
|
July 09 – Blasting continues, retaining walls being built. First permanent drainage fixtures in place.
|
August 09 – Retaining walls complete. Starting to grade and form final elevations
|
The girls give a sense of the size of the wall.
|
Building the upper retaining wall.
|
The lower retaining wall was made 100% out of material from the site.
|
April 2009
|
|
Almost done cutting down the trees
|
Trees are all down, now it’s time to stump
|
May 2009
Looking back towards Gerber Drive from the dome. Just starting to grade the area
June 2009
Blast, clear, and use for fill…
|
Laying protection from the blasting
|
Getting closer to the final elevation of the dome
|
And the blasting continues
|
Location, location, location. Nice to see some of these markers.
|
|
July 2009
Looking down on the dome area from the top of the hill.
|
|
Down at the elevation where the dome will sit.
|
The girls give a sense of the size of the wall.
|
Building the upper retaining wall.
|
The lower retaining wall was made 100% out of material from the site
|
Aerial Pictures
April 09 – Lot has been cleared, and in the process of being stumped.
|
April 09 – Everything is cleared. Beginning to grade.
|
August 09 – The entire site, along with Rt. 84.
|
August 09 – Focus on the area for the dome.
|
The upper section of the site where the dome and building will sit
|
|
August 2009
View from the lot next door.
|
Clearing the last of the rubble, and starting to formulate final elevations.
|
The dome is a BIG flat area...
|
September 2009
Foundation for the dome. Rough plumbing and electrical.
|
Pouring the foundation for the dome.
|
|
October 2009
Site Ready for Dome